澳门四不像论坛

Geraldton Port Maintenance Works

Client
Mid West Ports Authority
Construction site
Geraldton, WA
Period
2017-2019
Market
Marine

澳门四不像论坛 was engaged for various structural integrity and maintenance works at the Geraldton Port by Mid West Ports Authority (MWPA) and Marine & Civil.

Our Scope

Berth 4 Substructure Upgrade
澳门四不像论坛 was engaged by MWPA for fabrication and installation of beam work to the underside of Berth 4 at the Geraldton Port.

Berth 3 Concrete Repairs
澳门四不像论坛 was engaged by Marine & Civil to undertake various concrete repairs to the underside of Berth 3 at the Geraldton Port. The scope included:

  • Supply of scaffolding access to the underside of Berth 3 to facilitate concrete repairs
  • Structural integrity repairs to structural steel on the underside of the Berth, including platework and blast and paint

Fishing Boat Harbour Structural Integrity Works
澳门四不像论坛 was engaged by MWPA to complete various structural integrity works at the fishing boat harbour, including structural repairs, blasting and painting.

Berth 5 Fuel Piping & Walkway Removal
澳门四不像论坛 was engaged by Marine & Civil for removal of redundant fuel piping and walkway underneath Cargo Berth 5 at the Geraldton Port.

澳门四不像论坛 Integrated Services
Delivering across full asset lifecycles, from construction to asset integrity, maintenance & shutdowns.
Contact us now +61 8 9224 4600

Further Case Studies